Sunday June 26, 2016 thru Monday June 27, 2016 – I-270SB Lane Closures for Bridge Work
- 9 pm I-270SB reduced to two lanes between Sawmill Rd. and US 33.
- 9 pm the ramp from US 33WB to I-270SB closed. Detour: US 33WB to Avery-Muirfield Dr. to US 33EB to I-270SB.
- 9 pm ramp from I-270SB to US 33EB closed. Detour: I-270SB to Tuttle Crossing Blvd. to I-270NB to US 33EB.
- 11 pm I-270SB reduced to one lane between Sawmill Rd. and US 33.
- 5 am all lanes and ramps open.
Tuesday June 28, 2016 thru Thursday June 29, 2016 – I-270NB Lane Closures for Bridge Work
- 7 pm I-270NB reduced to two lanes between Tuttle Crossing Blvd. and US 33.
- 9 pm ramp from I-270NB to US 33WB closed. Detour: I-270NB to Sawmill Rd. to I-270SB to US 33WB.
- 9 pm ramp from US 33EB to I-270NB closed. Detour: I-270SB to Tuttle Crossing Blvd. to I-270NB.
- 11 pm I-270NB reduced to one lane between Tuttle Crossing Blvd. and US 33.
- 5 am all lanes open
Tuesday June 28, 2016 – US 33EB/WB Lane Closures for Pavement Work
- 8 pm US 33EB reduced to one lane between Avery-Muirfield Dr. and I-270.
- 8 pm US 33WB reduced to one lane between I-270 and Avery-Muirfield Dr.
- 5 am all lanes open
Don’t forget to like us on Facebook and please contact us with any questions or concerns. www.facebook.com/ODOTColumbusDistrict6.
For more information: Contact: Nancy Burton, District 6 Communications, at (614) 205-3131, Breanna Badanes, District 6 Communications, at (740) 833-8222.