JULY 11, 2016
Monday July 11, 2016 – I-270SB Lane Closures for Bridge Painting
- 7pm I-270SB reduced to three lanes between Sawmill Rd. and US 33.
- 9pm I-270SB reduced to two lanes between Sawmill Rd. and US 33.
- 9pm the ramp from US 33WB to I-270SB closed. Detour: US 33WB to Avery-Muirfield Dr. to US 33EB to I-270SB.
- 11pm I-270SB reduced to one lane between Sawmill Rd. and US 33.
- 5am all lanes open
Monday July 11, 2016 – I-270NB Lane Closures for Bridge Painting
- 7pm I-270NB reduced to two lanes between Tuttle Crossing Blvd. and US 33.
- 9pm the ramp from I-270NB to US 33WB closed. Detour: I-270NB to Sawmill Rd. to I-270SB to US 33WB.
- 9pm the ramp from US 33EB to I-270NB closed. Detour: I-270SB to Tuttle Crossing Blvd. to I-270NB.
- 11pm I-270NB reduced to one lane between Tuttle Crossing Blvd. and US 33.
- 5am all lanes and ramps open
Tuesday July 12, 2016 – I-270SB Lane Closures for Bridge Painting & Beam Work
- 7pm I-270SB reduced to three lanes between Sawmill Rd. and US 33.
- 9pm I-270SB reduced to two lanes between Sawmill Rd. and US 33.
- 9pm the ramp from US 33WB to I-270SB closed. Detour: US 33WB to Avery-Muirfield Dr. to US 33EB to I-270SB.
- 11pm I-270SB reduced to one lane between Sawmill Rd. and US 33.
- 5am all lanes and ramps open
Tuesday July 12, 2016 – I-270NB Lane Closures for Bridge Painting & Beam Work
- 7pm I-270NB reduced to two lanes between Tuttle Crossing Blvd. and US 33.
- 9pm the ramp from I-270NB to US 33WB closed. Detour: I-270NB to Sawmill Rd. to I-270SB to US 33WB.
- 9pm the ramp from US 33EB to I-270NB closed. Detour: I-270SB to Tuttle Crossing Blvd. to I-270NB.
- 11pm I-270NB reduced to one lane between Tuttle Crossing Blvd. and US 33.
- 5am all lanes and ramps open
Wednesday July 13, 2016 – I-270SB Lane Closures for Bridge Painting
- 7pm I-270SB reduced to three lanes between Sawmill Rd. and US 33.
- 9pm I-270SB reduced to two lanes between Sawmill Rd. and US 33.
- 9pm the ramp from US 33WB to I-270SB closed. Detour: US 33WB to Avery-Muirfield Dr. to US 33EB to I-270SB.
- 11pm I-270SB reduced to one lane between Sawmill Rd. and US 33.
- 5am all lanes open
Thursday July 14, 2016 – I-270SB Lane Closures for Bridge Work
- 7pm I-270SB reduced to three lanes between Sawmill Rd. and US 33.
- 9pm I-270SB reduced to two lanes between Sawmill Rd. and US 33.
- 9pm the ramp from US 33WB to I-270SB closed. Detour: US 33WB to Avery-Muirfield Dr. to US 33EB to I-270SB.
- 11pm I-270SB reduced to one lane between Sawmill Rd. and US 33.
- 5am all lanes and ramps open
Friday July 12, 2016 – I-270NB Lane Closures for Bridge Work
- 7pm I-270NB reduced to two lanes between Tuttle Crossing Blvd. and US 33.
- 9pm the ramp from I-270NB to US 33WB closed. Detour: I-270NB to Sawmill Rd. to I-270SB to US 33WB.
- 9pm the ramp from US 33EB to I-270NB closed. Detour: I-270SB to Tuttle Crossing Blvd. to I-270NB.
- 11pm I-270NB reduced to one lane between Tuttle Crossing Blvd. and US 33.
- 5am all lanes and ramps open