270 Lane Closures and Ongoing Work

Friday July 17, 2015 – 270 SB Lane Closures for Bridge Work

  • 9pm 270SB will be reduced to two lanes between Sawmill Rd. and Tuttle Crossing Blvd.
  • 9pm The ramp from 270NB to 33WB will be closed. The detour is 270NB to Sawmill Rd. 33 WB.
  • 11pm 270SB will be reduced to one lane between Sawmill Rd. and Tuttle Crossing Blvd.
  • 5am all lanes open

 

Ongoing Work

270/33 – 33 EB and WB is closed east of 270 to build four new bridges. The detour is 270 NB to Sawmill Pkwy to 270 SB to Tuttle Crossing Blvd. Two of the eight ramps at the interchange are also closed:

  • 33 WB to 270 SB
    Detour: 33 WB to 270 NB to Sawmill Pkwy. to 270 SB
  • 270 SB to 33 EB
    Detour: 270 SB to Tuttle Crossing Blvd. to 270 NB to 33 EB
    Completion: October 19.

 

Don’t forget to like us on Facebook and please contact us with any questions or concerns. www.facebook.com/ODOTColumbusDistrict6.

For more information: Contact: Nancy Burton, District 6 Communications, at (614) 205-3131, Breanna Badanes, District 6 Communications, at (740) 833-8222.