New Date Set for Opening of US 33 and Ramps in Dublin

Columbus (November 18, 2015) – December 11, weather permitting, is now the new target date to open US 33 along with the two loop ramps at I-270 and US 33 in Dublin.

By December, drivers can travel from one side of Dublin to the other, detour free.

Heavy rains in June and July saturated the soils and pushed more work into October and November. Since a lot of that work is paving, temperatures and conditions must remain consistently warm and dry which is rare during the Fall. To ensure the contractor gets all lanes and ramps open, the date is now December 11.

A small section of US 33 and the ramps from US 33 WB to 270 SB and 270 SB to US 33 EB closed June 8th for construction of the new bridges and ramps over the interstate.

Also in December another milestone will be reached for drivers on two ramps. Soon, there will be two lanes instead one on the exit ramp from eastbound US 33 to I-270 south towards Tuttle Crossing as opposed to one. The far right lane on the ramp ends at Tuttle. The left lane merges with I-270 south.

Drivers leaving Old Dublin heading west to access I-270 north will also be traveling on a new ramp.

Construction on the $71 million project started in March and is scheduled to be complete in 2017.

For up-to-date traffic information, construction information and road conditions, 24-hours a day, visit www.OHGO.com.

#

Don’t forget to like us on Facebook and please contact us with any questions or concerns. www.facebook.com/ODOTColumbusDistrict6.

For more information: Contact: Nancy Burton, District 6 Communications, at (614) 205-3131, Breanna Badanes, District 6 Communications, at (740) 833-8222.


Work Tonight on the interCHANGE Project

TONIGHT – Ramp 33EB to I-270 NB Closure

  • 9 p.m. ramp from US 33EB to I-270NB closed.
  • Detour: I-270SB to Tuttle Crossing Blvd. to I-270NB.
  • 5 a.m. ramp will open.

 

#

Don’t forget to like us on Facebook and please contact us with any questions or concerns. www.facebook.com/ODOTColumbusDistrict6.

For more information: Contact: Nancy Burton, District 6 Communications, at (614) 205-3131, Breanna Badanes, District 6 Communications, at (740) 833-8222.


Ramp from US 33 East to I-270 North Will Be Closed This Weekend

Friday, November 6, 2015 9 p.m. thru Monday, November 9, 2015 5 a.m. – Weekend Ramp Closure from US 33EB to I-270NB for pavement work

  • 9 p.m. ramp from US 33EB to I-270NB closed.
  • Detour: I-270SB to Tuttle Crossing Blvd. to I-270NB
  • 5 a.m. Monday ramp will open.

 

#

Don’t forget to like us on Facebook and please contact us with any questions or concerns. www.facebook.com/ODOTColumbusDistrict6.

For more information: Contact: Nancy Burton, District 6 Communications, at (614) 205-3131, Breanna Badanes, District 6 Communications, at (740) 833-8222.


I-270 SB Lane Restrictions This Week

Upcoming Work on the interCHANGE Project

Traffic impacts, night time only

Tuesday October 13, 2015 – I-270 SB Lane Closures for Pavement Striping

  • 7pm I-270SB reduced to three lanes between Sawmill Rd. and US 33.
  • 9pm I-270SB reduced to two lanes between Sawmill Rd. and US 33.
  • 11pm I-270SB reduced to one lane between Sawmill Rd. and US 33.
  • 5am all lanes open

 

Thursday October 15, 2015 – I-270 SB Lane Closure for Installation of Portable Concrete Barrier

  • 7pm I-270SB reduced to three lanes between Sawmill Rd. and US 33.
  • 5am all lanes open

#

Don’t forget to like us on Facebook and please contact us with any questions or concerns. www.facebook.com/ODOTColumbusDistrict6.

For more information: Contact: Nancy Burton, District 6 Communications, at (614) 205-3131, Breanna Badanes, District 6 Communications, at (740) 833-8222.


Upcoming Work on the interCHANGE Project

Traffic impacts, night time only

Sunday October 11, 2015 – I-270 NB Lane Closures for Bridge Work

  • 9pm I-270NB reduced to two lanes between Tuttle Crossing Blvd. and Sawmill Rd.
  • 9pm the ramp from US 33EB to I-270NB closed.
    • Detour: I-270SB to Tuttle Crossing Blvd. to I-270NB
  • 11pm I-270NB reduced to one lane between Tuttle Crossing Blvd. and Sawmill Rd.
  • 5am all lanes open

 

Monday October 12, 2015 – I-270 SB Lane Closures for Bridge Work

  • 7pm I-270SB reduced to three lanes between Sawmill Rd. and US 33.
  • 9pm I-270SB reduced to two lanes between Sawmill Rd. and Tuttle Crossing Blvd.
  • 11pm I-270SB reduced to one lanes between Sawmill Rd. and Tuttle Crossing Blvd.
  • 5am all lanes open

 

#

Don’t forget to like us on Facebook and please contact us with any questions or concerns. www.facebook.com/ODOTColumbusDistrict6.

For more information: Contact: Nancy Burton, District 6 Communications, at (614) 205-3131, Breanna Badanes, District 6 Communications, at (740) 833-8222.